The core regulations for SEG will be the same across the Energy world, things like price per kw is something the licensees/Energy Company do set.
@retrotecchie Always has solid advice when it comes to solar and being self sufficient. Like mentioned, you can charge the battery to be used at a later date, which % wise would be more beneficial in terms of saving money?
Have a solar related question? Pop me a tag! Need our customer service teams? Click here!📣 for ways to contact us
The core regulations for SEG will be the same across the Energy world, things like price per kw is something the licensees/Energy Company do set.
@retrotecchie Always has solid advice when it comes to solar and being self sufficient. Like mentioned, you can charge the battery to be used at a later date, which % wise would be more beneficial in terms of saving money?
Firstly I have been receiving SEG for 2 years and thought it would be a simple switch the same as it is for supplying energy.
No I have not applied for SEG as yet as it was not possible to get past the bit where you need to add your MCS (or equivelant) certificate number.
I am fully upto speed with Ofgem and its Guidance to Generators.
The core regulations from Ofgem for SEG may be the same across the energy world but there is also no legislative requirement for MCS certification.
It is at the SEG licencee's discretion they are not obliged to offer payments but they can make payments if they wish (SEG Guide To Generators 1.14).
my DNO UKpower networks has approved the installation and supplied an Export MPAN and are completely happy with my installation, which meets and exceeds the relevant version BS7671 electrical regulations that was in force at the date of installation (this was superceeded in September 2022).
So if it is purely an EonNext policy decision not to grant an export tariff to customers like myself.
I find this perplexing when I read in the news that coal power stations are being fired up because there is not enough grid capacity to power air conditioning systems in the summer when people like me could export solar energy to support such loads.
Seems like a massive missed opportunity to me!
MCS made sense when FIT tariffs were introduced to kick-start the immature solar generation industry but these days it adds no value beyond what the DNOs and BS7671 already cover.
Should you decide that you want to take this application forward then I will provide all requested documentation at that time.
Last edited by paulj; 20-11-23 at 19:57.
Reason: Forgot to add scematic
@paulj Thank you for the above. We need to get this amended as the statement is no longer applicable. It no longer affects eligibility etc.
I have highlighted this to the Operations Manager in the SEG department and hes confirmed with me today that 'we need to get this updated'
Thank you for highlighting this. The rules on SEG seem to change frequently, it's important 100% factual information is out there, especially on our websites etc.
@paulj No worries at all, it's just a term used, almost industry jargon if you wish.
Keep us updated on the application, it can take on average 2-4 weeks, some applications might take longer during busy periods however the team will get it sorted.
@paulj No worries at all, it's just a term used, almost industry jargon if you wish.
Keep us updated on the application, it can take on average 2-4 weeks, some applications might take longer during busy periods however the team will get it sorted.
I'm here if you need anything in the mean time 😀
I have submitted my application, only one issue I could see and that is I do not have the DNO's original G98 approval email (I have requested a copy from the DNO) I have added the approval reference number to my schematic outlined it in red, hopefully that will suffice until i get a copy of the original.
@paulj The reference is enough for us to raise the Export MPAN request. 😁
As I have said previously, I have been receiving SEG payments for 2 years I already have an export MPAN !
This should be a simple switch of provider not a fresh application for SEG.
As with every diverse community, there is always a mixture of opinions, knowledge as well as understanding - that’s what makes it such a great place to be! To make sure everyone gets the most out of our Community and feels good doing it, we’ve created some values below on how to be an awesome, positive member. So, take a read and then go for it!
We love having you all here in the Community and really hope you find some great advice and help from our other amazing members. As a community team, our main role here is keeping things ticking over, everyone safe and getting involved in some great conversations! We know many of you will have specific queries about your accounts and we want to keep your personal details safe so please don't post them here.
• Saying thanks goes a long way
• The community is a public website, so be careful
• Be kind, respectful and supportive
• It's a family-friendly community
• If you’re in a specific section or discussion, try to stay on topic
• One post is normally enough
• Be cool, don’t spam
We want to ensure that the community is safe and fair for everyone…
We all work hard to ensure everyone feels respected and supported while using the community, and keep that positive energy flowing. If a member or group is disrupting your experience without a genuine reason, you can report this to the community team quickly and easily by clicking the 3 dots on the post. Don’t worry about a thing, we’ll take it from there. If you get a message from the team about your behaviour, please try to work with us, as all we want to do is make this a positive place for everyone. In order to this, we have to uphold these Community Values and the Community Team has the final say.
The full Community Values can be viewed here
If you agree, please click the 'I agree' checkbox and press the 'Complete Registration' button below. If you would like to cancel the registration, click here to return to the Community homepage.
Although the administrators and moderators of E.ON Next Community will attempt to keep all objectionable messages off this site, it is impossible for us to review all messages. All messages express the views of the author, and neither the owners of E.ON Next Community, nor vBulletin Solutions Inc. (developers of vBulletin) will be held responsible for the content of any message.
By agreeing to these rules, you warrant that you will not post any messages that are obscene, vulgar,sexually-oriented, hateful, threatening, or otherwise violative of any laws.
The owners of E.ON Next Community reserve the right to remove, edit, move or close any content item for any reason.